£1m Rhosygilwen Mansion turbine refusal recommended again

The Rhosygilwen turbine application is to be decided by all councillors at County Hall (Pic: Pembrokeshire County Council/Pixabay)

A £1M SCHEME for a “20-storey-high” wind turbine at a Pembrokeshire mansion is recommended to be turned down later this week despite being twice backed by the council’s planning committee.

Mr and Mrs Glen Peters of Western Solar Ltd are seeking permission for a single turbine on land near the Grade II-listed Rhosygilwen Mansion, which includes an arts and functions building known as Neuaddydderwen.

Planners have repeatedly been recommended to refuse the scheme by officers, but backed it at both their March and April committee meetings.The March backing meant the application returned to the April meeting for ratification after a ‘cooling off’ period; the application having been deferred at the January meeting pending a site visit.

It was initially recommended for refusal in January for several reasons, including potential harm to the setting of the Grade-II-listed house and grounds, and fears of threats to the safe operation of West Wales Airport at Aberporth in neighbouring Ceredigion, some 9.5 kilometres away.

The last concern was later withdrawn.

Officers have said the scheme “would not protect or enhance the setting [of Rhosygilwen] but rather would result in significant harm to this interest of acknowledged importance”.

They have also warned any backing of the scheme against policy recommendations could set a precedent for similar developments.

Applicant Glen Peters has previously said the application for a turbine would ensure the long-term viability of Rhosygilwen, acquired some 30 years previously as a fire-damaged house that was about to be pulled down.

He has said that, despite 200-year-old Rhosygilwen using power from its solar farm, the first of its kind in Wales, it has been hit with “huge increases in importing energy from the grid” during the winter months.

Speaking at the April planning meeting, Mr Peters said the scheme as a whole was expected to cost “the best part of £1m”.

online casinos UK

Objector Paul Robertson-Marriott has said the “20-storey” turbine would have “a detrimental impact” on surrounding properties.

He said the majority of the power from the existing solar farm was fed into the grid rather than powering the house, believing the turbine proposal would “ride roughshod over the status of the listed building for economic benefit”.

“Why should the local community and environment be subject to an additional economic generator that causes environmental depredation?,” he asked members.

As the scheme would be a departure from the development plan it means it will have to be decided by full council, meeting on May 9, where it is recommended that council does not endorse the resolution of the planning committee, and refuses the application based on “significant harm” to the setting of Rhosygilwen.